Rte. 116/Hinesburg Road Construction Update

Home » City » Rte. 116/Hinesburg Road Construction Update

Thursday June 29, 2017

Preparation continues for the VTrans culvert replacement project on Hinesburg Road, with tree cutting and sign installation underway this week. Traffic control will be present allowing for one lane of travel.  A delay in delivery of materials has pushed out the date for installation of the new culvert in the Potash Brook section of Rte. 116 between Williston Road and Kennedy Drive. The road is expected to close to through traffic some time in early to mid-July; the road construction project should end by September 1. Pedestrians and bikers will still be able to cross through the construction zone and all abutting driveways/side roads will remain accessible.